您的当前位置:首页正文

屋面施工方案 精品

来源:帮我找美食网
 北京市轨道交通指挥中心二期工程 屋面施工方案

目 录

一、

编制依据 ··························································································· 1

施工图纸及施工组织设计 ································································ 1

1.1.

1.2. 标准、规范、规程及其他 ··································································· 1

二、 施工概况 ··························································································· 1

2.1. 建筑与结构设计概况 ········································································· 1 2.2.施工特点、重点与难点 ······································································· 3 三、 施工准备 ··························································································· 3

3.1.技术准备 ·························································································· 3 3.2.材料及机具准备 ················································································· 3 四、 施工安排 ··························································································· 4

4.1 总体施工安排安排 ·············································································· 4 4.2人员、时间安排 ················································································· 4 五、 主要施工方法及工艺 ··········································································· 5

5.1工艺流程··························································································· 5 5.2作业条件··························································································· 6 5.3找坡层施工 ······················································································· 6 5.4防水层施工 ······················································································· 7 5.5找平层施工 ······················································································ 11 5.6保温层施工 ····················································································· 12 5.7隔离层施工 ····················································································· 13 5.8屋面面砖铺设施工 ············································································ 14 5.9屋面细部做法 ·················································································· 14 六、 质量标准 ························································································· 19

6.1主控项目························································································· 19 6.2一般项目························································································· 19 6.3允许偏差项目 ·················································································· 20 七、 成品保护 ························································································· 20 八、 安全、环保措施 ··············································································· 21

8.1安全要求························································································· 21 8.2环保要求························································································· 21

第0页

北京市轨道交通指挥中心二期工程 屋面施工方案

一、 编制依据

1.1. 施工图纸及施工组织设计 施工图纸 施工组织设计 北京市轨道交通指挥中心二期工程 施工图设计(A版) 第二册 建筑 2012年3月 《北京市轨道交通指挥中心二期工程施工组织设计》 1.2. 标准、规范、规程及其他 序号 1 2 3 4 5 6 7 8 9 施工规范、规程名称 《屋面工程质量验收规范》 《建筑工程施工质量验收统一标准》 《屋面工程技术规范》 《高聚物改性沥青卷材屋面防水层施工工艺标准》 《北京市建筑工程施工安全操作规程》 《建筑工程资料管理规程 》 建筑通用构造图集 《北京市建筑长城杯工程质量评审标准 》 编 号 GB50207-2002 GB50300-2001 GB50345-2004 GY1005-1996 DBJ01-62-2002 DB11t695-2009 08BJ系列 DBJ/T01-70-2003 《工程建设标准强制性条文*房屋建筑部分》2009年版 DB11/510-2007 DBJ/T01-26-2003 10 公共建筑节能施工质量验收规程 11 建筑安装分项工程施工工艺规程 12 屋面防水施工验收规程 二、 施工概况

2.1. 建筑与结构设计概况

本工程屋面包括主楼、配楼、电梯机房、雨篷等屋面。主配楼屋面女儿墙采用钢筋混凝土结构(部分楼梯间顶层女儿墙采用砖墙砌筑). 屋面防水层采用3+3厚SBS改性沥青防水卷材防水等级为Ⅰ级,屋面保温层选用40厚SF憎水膨珠保温砂浆 (屋面导热系数0.48W/m2.k)。屋面排水方式有内排水和外排水两种,雨水管除说明外直径均为DN100。屋 面结构形式有平屋面和坡屋面(4-20轴/R-N轴结构找坡)两种 。

第1页

北京市轨道交通指挥中心二期工程 屋面施工方案

2.1.1不同种类屋面分布情况: 序号 1 2 3 部位 主楼,配楼屋面 楼梯、电梯间屋面 雨棚挑檐屋面 屋面编号 屋4 屋5 屋6 屋面 种类 上人屋面 不上人屋面 不上人屋面 排水坡度 主楼5%;配楼2% 2% 2% 面积 约5400 m2 约600 m2 约100 m2 2.1.2屋面主要施工做法如下:

上人屋面(屋面4) 配楼屋面; 48.05m屋面(11层顶结构平屋面);48.85m(11层顶结构坡屋面) 面层 基层 保温层 隔离层 DTA砂浆铺贴防滑地砖,DTG砂浆勾缝 20厚DS砂浆抹面,3m*3m分格,缝宽10,缝填密封膏 分层抹40厚SF憎水膨珠保温砂浆,每6m*6m分格缝,缝宽10,填密封膏 铺0.4厚聚氯乙烯塑料薄膜隔离层 (掺防渗密实剂);3mm厚热熔型聚酯SBS改性沥青防水卷材防水层 20厚防水水泥砂浆2遍(3+3厚)。 找平层 10厚DS砂浆找平层 最薄处10厚SF憎水性保温砂浆找2%坡;(4-20轴/R-N轴结构坡屋面取消找坡找坡层 层做法) 结构层 钢筋混凝土屋面板 不上人屋面(屋面5) 楼梯、电梯井屋面 面层 20厚DS砂浆抹面,3m*3m分格,缝宽10,缝填密封膏 保温层 分层抹40厚SF憎水膨珠保温砂浆,每6m*6m分格缝,缝宽10,缝填密封膏 隔离层 防水层 找平层 找坡层 铺0.4厚聚氯乙烯塑料薄膜隔离层 20厚防水水泥砂浆(掺防渗密实剂);3mm厚热熔型聚酯SBS改性沥青防水卷材2遍(3+3厚); 10厚DS砂浆找平层 最薄处10厚SF憎水性保温砂浆找2%坡 结构层 钢筋混凝土屋面板(女儿墙内面抹30厚SF憎水性灰,外抹3-5厚DP砂浆)

第2页

北京市轨道交通指挥中心二期工程 屋面施工方案

雨篷、挑檐 (屋面6) 面层 隔离层 保温层 防水层 结构层 20厚SF-ⅢM面层防水砂浆,振捣抹平压光,3m*3m分格,缝宽10,缝填密封膏。 30厚SF-ⅢD底层防水砂浆,振捣。 最薄处40厚SF憎水膨珠保温砂浆保温兼找坡层 1.5厚SF-T水泥基防水涂料 钢筋混凝土板 2.2.施工特点、重点与难点

2.2.1本工程于2012年3月底主体结构封顶。配楼屋面工程须在屋面主体结构验收合格后开始(屋面设备基础施工完成),定于4月1日开始屋面施工,主楼屋面待主体结构完成验收合格(屋面设备基础施工完成后)进行。

2.2.2施工时应设计要求屋面坡度及坡向,以免影响屋面排水效果。

2.2.3基层与突出屋面结构(女儿墙、墙、变形缝、天沟、排风道、出屋面口、设备基础等)的转角处,均先用水泥砂浆做成圆弧,再将柔性防水向上翘起规范规定高度。

2.2.4本工程屋面施工时间紧,工程量大, ,施工工序繁杂,质量要求高.

三、 施工准备

3.1.技术准备

3.1.1技术人员应对设计图纸进行认真的审核,明确各部位的节点做法,如发现图纸中有不明确事项,在施工前向设计人员提出,由设计人员进行确定。

3.1.2根据工程的特点、质量要求、工期要求、现场要求等,制定出详细的屋面工程施工方案,进行合理的施工安排,确保质量、进度、成本、现场等各项指标的顺利实现。

3.1.3施工前向施工队进行详细的交底,使其明确各部位的施工做法、操作工艺、施工要求等。

3.2.材料及机具准备

在正式开始施工前完成施工材料的招投标工作,并由项目部与其签订合同,确保各种人员、机具、材料按时、按量、按质进行供应。在开始施工前,技术室向供应方提供一份材料需求计划表,明确各期间的供应数量和供应要求等。本工程屋面分项工程各主要材料用量如下: 序号 1 2

名 称 SF憎水膨珠保温砂浆 SBS防水卷材 主要材料工程量统计表

规 格 主要要求 40mm厚 3mm厚 第3页

数量 1100m3 12000 m2 / / 备注 保温层 找坡层 防水层 北京市轨道交通指挥中心二期工程 屋面施工方案

3 4 5 6 DS砂浆 防水涂料 聚氯乙烯塑料薄膜 搅拌机 干拌砂浆 1.5mm厚 0.4mm厚 350型 水泥基 160 m3 120 m2 5900 m2 4台 找平层 防水层 隔离层 砂浆搅拌 3.3材料运输:屋面装修阶段的材料采取外用电梯垂直运输,外用电梯无法到达处采用原

结构塔吊运输,同时配合以手推车在屋面内水平运输。

四、 施工安排

4.1 总体施工安排安排

根据现场施工的实际情况,按照结构完成的先后顺序确定屋面施工的顺序: 配楼屋面 (26.9m屋面;31.4m屋面;32.6m屋面) 11层顶结构平屋面 (48.05m屋面) 钢屋面结构坡屋面(48.85m屋面) 顶层楼梯电梯屋面(3#、4#、5#、6#楼梯顶棚屋面52.1m屋面) 阳台、雨棚及其余楼梯屋面。 4.2人员、时间安排 4.2.1组织机构

组 长:肖舰

副组长:蕫延军 王慧斌 邵永欣 吕豪 王晓兵

组 员:钱明星 金传江 南宝国 白爱国 张毅 严星 韩俊 蒋爱平 白爱国 夏卫红

李明亮 贾永迁 赵文来

化中信 王旺

4.2.2 人员分工

钱明星 南宝国 现场总负责 张毅 金传江 白爱国 南宝国 张毅 金传江 现场技术,各专业之间协调 各施工队伍的进场安排,现场管理等协议的签定;施工队伍的进场教育和现场的各种教育;现场进度、人员安排,各施工队伍之间调度协调 施工方案的编制,技术指导以及与其它专业之间的技术配合,施工质量控制,组织材料的进场验收、报验 技术交底的编制,现场技术指导,相关隐检资料的填写,参与材料的进场检验 根据技术交底的要求对现场的施工进行质量检查、监督,相关质量资料的收集整理,负责向严星 贾永迁 韩俊 姜学友 监理报验,针对现场的质量问题及时下发质量问题整改通知,并跟踪督促、检查

第4页

北京市轨道交通指挥中心二期工程 屋面施工方案

严星 赵文来 李明亮 王旺 蒋爱平 化中信 张玉干 白爱国姜学友 夏卫红 化中信 对进场需要进行复试的材料委托试验室进行检验,并负责相关资料的收集整理 根据技术要求,对现场的找坡标高进行控制 根据屋面工程的进度计划,进行现场工作的安排、协调和现场文明施工管理;参与材料的进场检验 现场安全负责及相关内业资料和动火证的发放检查 组织相关材料的进场,钢管等周转材料的进退场,参与材料的检查验收,并负责厂家资料的收集整理 4.2.3劳动力计划

4.2.3.1装修队伍:负责找坡层、找平层、防水保护层、屋面砖铺贴的施工,计25人。 4.2.3.2防水队伍:负责防水施工以及蓄水试验,计12人。

4.2.3.3保温队伍:负责保温的施工,并根据总进度计划分段进行施工,计16人。

4.2.3.4施工工期计划:屋面施工根据实体施工进度进行,找坡材料必须提前一周进场,其余各种材料按施工进度分别进场.屋面施工计划于主体结构验收完成后开始施工,即3月底开始进行施工,先施工找坡、找平层,在外墙钢结构及保温完成拆除吊篮后进行防水、保温及屋面砖铺贴施工。

4.2.3.5施工节点计划表:

主要施工工序及各工序完成的时间节点 施工部位 找坡、找平层 配楼屋面 48.05m屋面 48.85m屋面 楼梯顶棚屋面4月18日 52.1m屋面 雨棚,阳台 4月20日 4月24日 4月26日 5月1日 4月21日 4月24日 4月29日 3月28日 4月10日 4月15日 防水层 3月30日 4月15日 4月18日 保温层 4月5日 4月18日 4月22日 面层 4月15日 4月24日 4月27日 五、 主要施工方法及工艺 5.1工艺流程

5.1.1上人屋面工艺流程

施工准备→基层处理及出屋面管根等处理→找坡层及找平层施工→防水层施工→ 附加隔离层 →保温层施工→DS砂浆抹面层施工→ 防滑地砖铺贴 5.1.2不上人屋面工艺流程

第5页

北京市轨道交通指挥中心二期工程 屋面施工方案

施工准备→基层处理及出屋面管根等处理→找坡层及找平层施工→防水层施工→ 附加隔离层 →保温层施工→DS砂浆抹面层施工 5.1.3雨棚及阳台工艺流程

施工准备→基层及出屋面结构处理→防水涂料施工 →保温兼找坡层→防水砂浆层施工→砂浆面层。

5.2作业条件

5.2.1顶层结构施工完,现浇女儿墙已浇筑完毕,砌筑女儿墙已砌筑完成。设备基础完成,屋面杂物处理完毕。

5.2.2水电管出屋面部分、烟风道、透气管道已施工完毕。 5.2.3屋面内排雨水斗已安装完毕。

5.2.4穿结构的管根用膨胀细石混凝土塞堵密实。 5.2.5提前对进场的各种材料进行复试和有见证取样。

5.3找坡层施工

5.3.1 材料及要求:

5.3.1.1 采用 SF憎水性膨珠保温砂浆最薄处10厚。

5.3.2主要机具:搅拌机、手推车、压滚、平铁锹、计量器、筛子、喷壶、铝合金靠尺、笤帚、铁抹子、水平刮杆、水平尺等。

5.3.3施工工艺

5.3.3.1根据墙上500mm水平标高线按2%找坡,根据坡度将铺设保温砂浆的厚度线以贴饼形式体现出来,找坡层最薄处10mm,水落口周围直径500mm范围内坡度不应小于5%。

5.3.3.2冲筋贴灰饼:根据坡度要求和测量人员放线拉线找坡贴灰饼,顺排水方向冲筋,冲筋间距为1.5m。冲筋后进行找坡层施工。找坡层的坡度必须准确,符合设计要求。

5.3.3.4铺设保温砂浆:将拌和均匀的拌和料铺设于屋面,按照贴饼标高铺设基本找坡。

5.3.3.5刮平、滚压:以找坡贴饼为标志,控制好虚铺厚度,用铁锹粗略找平,然后用木刮杠刮平。再用压滚往返滚压,并随时用2m靠尺检查平整度,将多出部分铲掉,凹处填平,直到滚压平整出浆为止。对于墙根、边角、管根周围不易滚压部位用木板拍打密实。

第6页

北京市轨道交通指挥中心二期工程 屋面施工方案

5.3.3.6养护:找坡层施工完毕后进行洒水养护,严禁上人乱踩,待其凝固后方可进行下道工序施工。

5.3.3各楼屋面坡度走向见附图。 5.3.4质量要求:

1、 找坡层材料必须符合设计图纸和有关标准的规定。 2、 允许偏差项目

找坡层厚度的允许偏差

项 目 表面平整度 标高 厚度 允许偏差(mm) 10 ±10 ≤设计厚度的1/10 检 验 方 法 用2m靠尺和楔形塞尺检查 用水准仪检查 用钢针和尺量检查 5.4防水层施工

5.4.1材料要求

5.4.1.1所使用的防水材料必须有出厂合格证及相关部门颁发的防水材料使用认证书,材料必须符合设计要求,材料进场后必须按规定进行现场取样复试,复试合格后方准使用。

5.4.1.2卷材:SBS改性沥青防水卷材,两层做法,卷材的各项性能及外观质量应符合以下要求:

改性沥青防水卷材物理性能

改性沥青防水卷材外观质量

项 目 孔洞、缺边、裂口 边缘不整齐 胎体露白、未浸透

第7页

质 量 要 求 不允许 不超过10mm 不允许 北京市轨道交通指挥中心二期工程 屋面施工方案

纤维布材料粒度、颜色 每卷卷材的接头 均匀 不超过1处,较短的一段不应小于1000mm,接头处应加长150mm 5.4.1.3材料的贮存、保管:卷材应贮存在阴凉通风的室内,避免雨淋、日晒和受潮,严禁接近火源,贮存环境温度不得高于45摄氏度,应直立堆放,堆放高度不超过两层,并不得倾斜或横压,避免与化学介质及有机溶剂等有害物接触。

5.4.1.4配套材料

a)基层处理剂:采用冷底子油。

b)接缝密封材料:采用改性沥青密封材料,用于立面防水卷材收头密封及外墙管根等特殊部位的粘结处理,密封材料的各项性能应符合下表的要求。

改性沥青密封材料物理性能 项目 拉伸粘结性 (不小于) 耐热度 80℃,5h下垂值(不大于) 柔 性 -10℃ 施工缝宽度 5.4.2作业条件

5.4.2.1防水卷材合格证、准用证、检验报告、复试报告齐全,材料现场见证取样送检合格。防水施工单位资质齐备,现场管理人员和操作人员持证上岗,施工人员操作时要穿工作服,软底鞋并带手套。

5.4.2.2施工前对施工队伍进行技术、安全等交底。

5.4.2.3防水卷材和配套材料均为易燃材料,集中存放,有专人管理,并准备好干粉灭火器,严防火灾发生。

5.4.2.4 砂浆找平层施工完毕,并经养护后干燥、平整、牢固,无空鼓开裂、不起砂。

5.4.2.5屋面女儿墙、烟风道出屋面及水箱间外墙作好泛水,阴阳角处抹成半径50mm的圆弧形。

5.4.2.6涂冷底子油前,将基层表面浮灰、垃圾等其它杂物清理干净。 5.4.2.7电梯间、楼梯间屋面等高处屋面排水的水落口已安装完成。

第8页

指标 125mm 4mm 无裂纹 25mm 北京市轨道交通指挥中心二期工程 屋面施工方案

5.4.3施工工艺 5.4.3.1工艺流程:

基层清理→涂刷基层处理剂→附加层→卷材铺贴→卷材收头粘结→卷材接头密封→淋水试验

5.4.3.2基层清理:涂刷冷底子油前,仔细将基层表面的垃圾、尘土等清除干净,必要时可采用喷灯局部喷烤,但喷烤时间不宜过长,防止爆裂、起砂。

5.4.3.3基层含水率检测:剪一块1m²的卷材平铺于基层表面,静臵3-4小时,然后揭开卷材观察其下方基层面及防水卷材,如未见水印,即可铺设防水层。

5.4.3.4涂刷基层处理剂:在基层表面满刷一遍冷底子油,底油的施工也按先高后低、先远后近、先立面后平面的顺序进行。同一屋面上先涂刷排水较集中的水落口、天沟、檐口等节点,再进行大面积的涂布。屋面转角及立面的涂刷层应薄涂多遍,不得有流淌和堆积现象。涂刷要均匀、不透底、遮盖率100%,底油总厚度不得小于3mm。在底油实干前,不得在防水层上进行其它施工作业,不得上人和堆放物品。

5.4.3.5铺贴附加层:屋面女儿墙、排风道出屋面、水箱间、楼梯间(电梯间)外墙根部、阴阳角部位加铺一层同质卷材附加层,将卷材裁成相应的形状进行热熔满贴,宽度500mm,附加层施工必须粘贴牢固。水落斗周围与屋面交接处,应做密封处理,并加铺两层附加层,附加层深入水落斗的深度不得小于100mm。

5.4.3.6确定铺贴方向、弹基准线:冷底子油涂刷完毕3小时后,手摸感觉不粘即可根据卷材的宽度和搭接的规定,在冷底子油上进行弹线。弹线由排水较集中的部位开始,遵照由低到高、先平面后立面的顺序弹基准线。

5.4.3.7做样板:在大面积铺贴施工前,施工队要按照技术要求及细部做法在配楼做100m2样板,经项目验收合格后,进行大面积施工。

5.4.3.8卷材铺设:卷材施工时应先做好节点、附加层和屋面排水比较集中等部位的处理,然后从流水坡度的下坡开始由低处向高处铺贴,顺着流水方向,并使卷材的长向和流水坡向垂直,两层卷材必须平行铺贴,禁止垂直铺贴,铺贴时先平面后立面。铺贴平面立面相接茬的卷材,由下向上进行,使卷材紧贴阴阳角,不得有皱折和空鼓等现象。

5.4.3.9卷材搭接:相邻卷材的短边搭接不小于80mm,长边搭接不小于80mm。 5.4.3.10卷材起始端粘贴:采用满粘法。将卷材臵于起始端位臵,对好长短方向搭接缝,滚展卷材1000mm左右,掀开已展开的部分,开启喷灯点火,喷灯头与卷材保持50-100mm距离,与基层呈30°-45°角,同时加热卷材底面热熔胶面和基层,至热熔胶

第9页

北京市轨道交通指挥中心二期工程 屋面施工方案

面出现黑色光泽、发亮至稍有微泡出现,慢慢放下平铺于基层,然后排气辊压使卷材与基层粘结牢固。

5.4.3.11滚铺:卷材起始端铺贴完成后即可进行大面积滚铺。持火人位于卷材滚铺的前方,按上述方法同时加热卷材和基层,加热范围为整个卷材面,加热程度要均匀。推滚卷材的人蹲在已铺好的卷材起始端上面,等卷材充分加热后缓缓推压卷材,并随时注意卷材的平整顺直和搭接宽度。其后紧跟一人用棉纱团等从中间向两边抹压卷材,赶出气泡,并用刮刀将溢出的热熔胶刮压接边缝。找平层分格逢处应空铺,空铺宽度为100mm。

5.4.3.12卷材末端收头:接缝处用喷灯热熔卷材边缘,待表面熔化后随即用小铁抹子将边缝封好,再用喷灯均匀细致地将边缝烤一遍保证接头密封,以免翘边,立面卷材的收头应按附图要求在女儿墙规定高度处收头,收头处用金属压条钉严,钉子间距500mm,并用密封材料封严。

5.4.3.13防水层蓄水试验:蓄水试验前,对排水管道进行检查,确保无漏水隐患和对楼内的成品造成破坏;防水施工完毕后经隐蔽工程验收后进行24小时蓄水试验,蓄水高度与防水层最低点持平,合格后方可进行保护层施工(坡屋面进行泼水试验)。

5.4.4质量要求 5.4.4.1.主控项目

1改性沥青SBS防水卷材和胶粘剂的规格、性能、配合比必须符合规范要求,有合格的出厂证明、检验报告等。

2卷材防水层及其转角处、落水口、烟风道、泛水等细部做法,必须符合设计要求和施工验收规范的规定。

3防水层严禁有破损和渗漏现象发生。 5.4.4.2.一般项目

1卷材防水层的基层平整,基层洁净、平整,无空鼓、松动、起砂和脱皮现象;基层阴阳角成弧形或钝角。

2卷材防水层的搭接缝粘接牢固,密封严密,不得有损伤、皱折、翘边和鼓泡等缺陷。

3卷材防水层的保护层与防水层粘结牢固,结合紧密,厚度均匀一致。

4防水卷材铺贴附加层的宽度符合规范要求;分层的接头搭接宽度符合规范的规定,

第10页

北京市轨道交通指挥中心二期工程 屋面施工方案

接头嵌填牢固。

5卷材搭接宽度的允许误差为-10mm。 5.4.5防水施工注意事项

5.4.5.1卷材铺贴应平整顺直,搭接尺寸准确,不得扭曲、皱折。

5.4.5.2热熔法施工时,不得过分加热或烧穿卷材。卷材表面热熔后立即滚铺卷材,滚铺时应排除卷材下面的空气,使之平展,并应辊压粘结牢固。卷材接缝部位必须溢出热熔的改性沥青。

5.4.5.3防水施工过程中如遇雨天,禁止施工,并准备大面积塑料布将防水施工成品进行遮挡,避免淋雨、受潮;雨后要将基层凉晒三至四天,并进行基层含水率试验,符合要求后方能继续进行防水层施工。

5.5找平层施工

5.5.1 材料及要求: 5.5.1.1采用 10厚DS砂浆。

5.5.2作业条件:找平层施工前,找坡层应进行检查验收完毕,并办理隐检手续。 5.5.3施工工艺

5.5.3.1基层清理:将找坡层表面的松散杂物清扫干净,突出基层表面的灰渣等粘接杂物要铲平,不得影响找平层的有效厚度。

5.5.3.2洒水湿润:抹找平层水泥砂浆前,适当洒水湿润基层,利于基层与找平层的结合。

5.5.3.3冲筋、贴饼定标高:按1.5m间距贴灰饼,然后按流水方向以间距1.5m冲筋。

5.5.3.4铺装水泥砂浆:按分格块铺设砂浆,用刮杠靠冲筋条刮平,找坡后用木抹子搓平,用铁抹子压光,待浮水沉失后,以人踏上去有脚印但不下限为度,再用铁抹子压第二遍即可。

5.5.3.5找平层做至女儿墙顶,所有阴阳角均抹成圆弧形,圆弧半径R=50mm(用酒瓶抹)。

5.5.3.6分格缝:找平层按不大于6m设臵20mm宽分格缝,并用密封膏封严。分格缝布臵图见细部做法分格缝布臵图。

5.5.3.7养护:找平层抹平、压实以后24h可浇水养护,养护期为7天,经干燥后

第11页

北京市轨道交通指挥中心二期工程 屋面施工方案

铺设防水层。

5.5.4质量要求 5.5.4.1主控项目:

1 水泥砂浆找平层的材料质量及配合比,必须符合设计要求。 2 屋面找平层的坡度必须符合设计要求。 5.5.4.2一般项目

1 基层与突出屋面结构的交接处和基层的转角处,均做成圆弧形,且整齐平顺。 2 水泥砂浆找平层平整、压光、密实,不得有酥松、起砂、起皮、裂纹、空鼓、蜂窝、麻面等缺陷。

3 水泥砂浆找平分格缝的位臵及间距(纵、横两个方向均不大于6m)符合设计要求。 4屋面找平层允许偏差项目如下表所示:

屋面找平层的允许偏差和检验方法

项次 1 2 项目 表面平整度 标高 偏差(mm) 3 3 检查方法 用2m靠尺和楔形塞尺检查 用水准仪检查 5.6保温层施工

5.6.1材料及要求:保温层采用40厚 SF憎水性膨珠保温砂浆。保温砂浆进场后必须采取防雨、防潮措施。

5.6.2 主要机具:手推车、小白线、水平尺等。 5.6.3 施工工艺

5.6.3.1工艺流程:基层清理→弹线确定标高→保温层铺设。

5.6.3.2基层清理:将混凝土屋面上的杂物、垃圾等清理干净,保持干燥,基层验收合格并作隐检记录。

5.6.3.3保温层设臵:分层抹保温砂浆,共40厚,保持表面平整。 5.6.3.4已铺完的保温层,不得在其上面行走或运输小车和堆放重物。 5.6.4质量要求 5.6.4.1主控项目:

1保温材料的强度、密度、导热系数和吸水率,必须符合设计要求和施工验收规范的规定。

2保温板的含水率必须符合设计要求和施工验收规范的规定应紧贴基层铺设,铺平垫稳,标高正确。

第12页

北京市轨道交通指挥中心二期工程 屋面施工方案

5.6.4.2一般项目

1紧贴(靠)基层,铺平垫稳,拼缝严密,找坡正确。 2 允许偏差项目如下表所示:

屋面保温层的允许偏差和检验方法 项次 项目 允许偏差(mm) 检查方法 1 表面平整度 4 用2m靠尺和楔形塞尺检查 2 保温层厚度 ±3 用钢针插入和尺量检查 5.7隔离层施工

5.7.1材料及要求:隔离层材料采用铺设0.4厚聚氯乙烯塑料薄膜,在铺设施工前,计算出需要铺设聚氯乙烯塑料薄膜的面积,采购回来后,得到监理认可,符合设计要求后,方可投入使用。

聚氯乙烯塑料薄膜的各项物理力学和渗透性等指标必须符合设计要求,对存放过长或已出现老化现象的聚氯乙烯塑料薄膜、一律不进、不使用。

5.7.2 施工工艺

5.7.2.1工艺流程:基层清理→弹线确定铺设走向 →聚氯乙烯塑料薄膜

5.7.2.2基层清理:为了便于铺设,铺塑料薄膜前,防水层表面先进行平整。使塑料薄膜能与基层面紧贴。

5.7.2.3塑料薄膜铺设:沿着基层表面进行铺设,相邻塑料薄膜的搭接长度不小于1m。先将成卷的塑料薄膜放到基层面上,位臵正确后,逐渐向前铺设,如出现偏差,则人工进行纠偏,确保位臵正确到位。

5.7.2.4塑料薄膜应边铺设,边压载,使塑料薄膜紧贴基层底面,以保证塑料薄膜的铺设质量。压载采用袋装砂,间距为1~2m。为防止撕裂,塑料薄膜铺设时要保持平顺,呈松弛状,不宜张紧,另外要留有一定的富裕量以适应变形。铺设过程中如出现破损或孔洞时及时进行修补,修补采用与塑料薄膜相同的材料,用pvc胶缝合,且缝接宽度不小于设计搭接宽度。

5.7.3塑料薄膜施工注意事项

5.7.3.1 塑料薄膜铺设应尽量平整,避免扭曲和皱折,应保持平顺、松紧适度。塑料薄膜与基层应压平贴紧,以保证安全。

5.7.3.2 塑料薄膜运输过程中和运抵工地后应妥善保管,应避免长时间日晒,防止粘结成块,且尽量减少装卸次数。

5.7.3.3 塑料薄膜的拼接方式及搭接长度(200mm)符合施工规范要求。

第13页

北京市轨道交通指挥中心二期工程 屋面施工方案

5.8屋面面砖铺设施工

5.8.1材料及要求:防滑面砖面砖的品种规格应由设计及业主确认,封样后可大批量采购,屋面粘粘贴面砖应执行样板先行的原则.

5.8.2 施工工艺

5.8.2.1工艺流程:基层清理并找平→弹线确定面砖铺设走向 → 排砖 → 面砖铺贴→ 勾缝

5.8.2.2基层清理平整:为了便于铺设,铺砖前基层表面先进行平整。

5.8.2.3按照屋面泛水的布局进行排砖,根据屋脊或分水岭处开始向两侧依次放线.然后沿着纵横方向开始放线.灰缝暂定为5-7mm.

5.8.2.4根据放好的线预排面砖,特别是灰缝的调整,核实无误。

5.8.2.5虚铺砂浆找平层,用木抹子摊平拍实, 铺设厚度20mm,然后进行屋面砖试铺,对好纵横缝,用橡皮锤敲击屋面砖中间,振实砂浆至铺设高度后,将试铺合适的屋面砖掀起移至一边,满刮一层水泥粘结浆结合层,再铺上屋面砖,铺时要四角同时落下,用橡皮锤轻轻敲平,随时用水平尺或直板尺找平。

5.8.2.6面砖铺贴完成后进行养护,3日后检查是否有空鼓,不平整的面砖,达到质量要求后进行勾缝。

5.8.3面砖施工注意事项:

5.8.3.1以下水口为中心800×800mm范围内,也要预留出来,重新进行细部排砖。细部排砖,砖缝宽窄要与大面砖保持一致,细部排砖部位:天沟、檐沟、雨水口泛水、屋面砼设备登台

5.8.3.2每块砖铺好后,向两侧和后退方向顺序逐块铺砌,板块间灰缝要一致,拉通线对灰缝的平直度进行控制,安装好的屋面砖板块应整齐平整,横竖缝对齐。

5.9屋面细部做法

5.9.1钢筋混凝土女儿墙厚200mm,女儿墙顶防水收口做法见图;

第14页

北京市轨道交通指挥中心二期工程 屋面施工方案

5.9.2井道出屋面结构防水收口做法见下图,风道砌筑时在出屋面结构250mm标高处留槽,防水卷材收口在120宽挑弦底部。

第15页

北京市轨道交通指挥中心二期工程 屋面施工方案

5.9.3设备基础防水收口做法见下图,卷材收口高度大于等于250mm,并在地脚螺栓周围做密封处理。

第16页

北京市轨道交通指挥中心二期工程 屋面施工方案

5.9.4雨水口的安装:

本工程设计中屋面排水分为内排水和外排水方法。内排水为直式水落口。外排水电梯井及楼梯间屋顶排水为镀锌铁皮水舌。按照原设计图纸上给定的雨水口的位臵,检查在结构施工时留下的洞口位臵,在安装前将预留洞口处理好,墙体预留洞部位将泡沫剔凿干净。

直式水落口周围直径500mm范围内坡度不应小于5%,并应用防水涂料涂封,其厚度不应小于2mm。水落口与基层接触处应留宽20mm、深20mm凹槽,嵌填密封材料。

5.9.5出屋面管道防水收口做法:伸出屋面管道周围的找平层应做成30mm圆锥台,

第17页

北京市轨道交通指挥中心二期工程 屋面施工方案

管道周围与找平层之间应留凹槽,用密封材料嵌填密实,管道根部四周增设防水附加层,宽度250mm,高度250mm,防水收头处用金属箍紧固,并用密封材料封严。大样图如下:

5.9.6分格缝:上人、不上人屋面及雨篷的保护层及各屋面的找平层设臵分格缝,间距为6*6m,缝宽20mm,密封材料填实,布臵见附图。女儿墙立面抹灰为防止裂缝按照10m进行分缝,缝宽20mm,分格缝用柔性密封材料填实。

5.9.7出屋面门洞口:本工程设计屋面上均设有机房层,机房出屋面门洞口踏步做法如下图所示,采用砖砌体,砌体均用MU15灰砂砖,M5水泥砂浆,砖砌踏步每端宽出门洞口250,用1:2水泥砂浆抹面20厚。

5.9.8天沟:主楼屋面女儿墙四周设臵钢制排水天沟,天沟宽度400mm,高度400mm,天沟

第18页

北京市轨道交通指挥中心二期工程 屋面施工方案

底标高为47.9m,天沟下方设臵直落式排水系统.

5.9.9屋面施工缝处理:主楼外墙与配楼屋面女儿墙交接处存在施工缝,做法详见下图

六、 质量标准 6.1主控项目

6.1.1保温材料的强度、容重、导热系数和含水率等必须符合设计要求和《屋面工程质量验收规范》(GB50207-2002)及《建筑节能工程施工质量验收规范》(GB50411-2007,为节能规范)的规定。

6.1.2找坡层材料必须符合设计图纸和有关标准的规定。

6.1.3找坡施工配合比、铺设密实度应符合设计要求和《屋面工程技术规范》(GB50345-2004)的规定。

6.1.4找平层采用的砂浆,所用原材料及配合比必须符合设计要求和施工规范的规定。 6.1.5找平层的坡度必须符合设计要求。

6.1.6防水卷材的规格、性能、配合比必须达标,并有合格的出厂证明。 6.1.7防水层不得有渗漏和积水现象。

6.1.8细部防水构造必须符合设计要求和规范要求。

6.1.9屋面施工时,各道工序完成后,必须经过验收并办理相应手续方可进入下一道工序。

6.2一般项目

第19页

北京市轨道交通指挥中心二期工程 屋面施工方案

6.2.1保温材料应紧贴基层铺设,铺平垫稳,拼缝严密。 6.2.2找坡层与基层间不得有空鼓和表面积散现象。

6.2.3突出屋面的管道和阴阳角等部位做成圆弧型,圆弧半径R=50mm,水落口周围500mm范围内应做成略低的凹坑。

6.2.4找平层无空鼓、起砂,表面平整,用2m长直尺检查,直尺与基层间隙不应超过5mm,阴阳角要弧形或钝角。

6.2.5冷底子油涂刷要均匀,不得有漏刷、透底和麻点现象。 6.2.6防水卷材铺附加层接头要嵌牢固。

6.2.7卷材粘结要牢固,无空鼓、损伤、滑移翘边、起泡、皱折等缺陷。 6.2.8面层应设臵分格缝,与卷材防水层间应设臵隔离层。 6.2.9卷材的铺贴方向正确,搭接宽度允许偏差为-10mm。

6.2.10面砖应铺砌平整、坚实、洁净、线路顺直、勾缝严密,不得有空鼓、松动,脱落和裂缝、缺棱掉角,污染等缺陷。

6.3允许偏差项目

保温层厚度的允许偏差

项目 保温层厚度 允许偏差(mm) ±2.5 找坡层厚度的允许偏差

项 目 表面平整度 标高 厚度 允许偏差(mm) 10 ±10 ≤设计厚度的1/10 找平层厚度的允许偏差

项 目 平整度 允许偏差(mm) 5 检验方法 用2m靠尺和塞尺检查 检 验 方 法 用2m靠尺和楔形塞尺检查 用水准仪检查 用钢针和尺量检查 检验方法 用钢针插入和尺量检查 七、 成品保护

7.1保温层的成品保护

1.在已铺好的松散、板状或整体保温层上不得直接行走、运输小车,行走路线应铺垫脚

第20页

北京市轨道交通指挥中心二期工程 屋面施工方案

手板;

2.保温层施工完成后,应及时铺抹细石砼找平层,减少受潮和进水; 7.2找坡层、找平层的成品保护

1.抹好的找平层上推小车运输时,应先铺脚手板车道,防止破坏找平层; 2.雨水口、内排水口等部位应采取临时措施保护好,防止堵塞和杂物进入; 7.3防水层的成品保护

1.刚涂刷好的防水底胶层,应及时采取保护措施,严禁上人;

2.突出地面管根、地漏、排水口,阴阳角等处和周边防水层不得碰损,部件不得变位; 3.防水施工过程中,未固化前不得上人走动,以免破坏防水层,造成渗漏的隐患; 4.防水施工过程中,应注意保护有关门口、墙面等部位,防止污染成品

八、 安全、环保措施

8.1安全要求

1. 防水施工所有的材料均属易燃物,贮存、运输过程必须严禁烟火,在现场施工时,

设专人看护,发现火情,立即报警。现场喷灯,专人使用,不能随意点火。现场必须配备相应的消防器材。

2. 施工人员必须穿软底鞋,不得穿硬底鞋或带钉子的鞋进入施工现场,并应配备相应

的保护用品,带好安全帽。 3. 所有洞口临边防护按安全交底执行。 4. 施工人员必须戴好安全带及安全帽。

5. 施工机械安全管理:施工电梯的地基安装和使用要符合使用规定,并有验收手续,

经检验合格后,方可使用,使用中,定期进行检测。电梯安全装臵必须齐全、灵敏、可靠,执行额定重量人员。

6. 临时用电安全防护管理:临时用电必须按规范的要求,依据施工组织设计(方案)

执行,建立必要的档案资料。

7. 消防安全管理措施:严格工地使用明火审批手续,需要运用明火的当天可提出申请。

8.2环保要求

1. 松散材料一律在库房内封闭保存,避免造成扬尘污染和浪费;

2. 现场施工时对少量的洒落灰要及时清理,并用编制袋集中收集起来重复利用; 3. 砂浆搅拌机使用完毕后要及时清理,避免在下次使用中造成不必要的机械损耗和噪

第21页

北京市轨道交通指挥中心二期工程 屋面施工方案

声的增加;

4. 已拌好的砂浆,在运送过程中要避免遗漏,对少量遗漏的要及时清理; 5. 操作人员在施工时应佩带口罩、手套,防止有害气体的吸入。 6. 在施工过程中,做好人工通风工作,防止发生中毒事故。

7. 安全员在施工现场巡回检查,如发现火情、中毒等意外事件,及时处理。 8. 雨、雾、大气湿度过大及六级以上大风天气不宜施工。 9. 施工现场配备消防设备。

10. 施工现场应清除易燃物及易燃材料,消防道路应保证畅通。

11. 施工使用的易燃物及易燃材料应存放于指定地点,并有防护措施及专人看管。 12. 喷灯、喷枪及易燃品等,下班后必须放入有人管理的指定仓库。

施工完毕后剩余的材料容器及少量废料严禁随意丢弃、倾倒,及时回收处理,以免造成污染。

第22页

因篇幅问题不能全部显示,请点此查看更多更全内容

Top